Hi

I am using multiple overlapping zones (total as built areas, Rooms, Zones in the Building, etc...) most of them on top of each other because they are in different categories and different layers.

I need to Schedule objects and I want to show the room in which the objects are. How can I be sure that it will chose the Room Zone and not the Built Up area Zone? I tried turning on/off the layer, it doesn't work.

Thanks in advance!!

Nando

_________________
Nando Mogollon

www.nandomogollon.com
www.openBIMer.com
mail@nandomogollon.com
@openbimer
Now in Australia!
Revit 2017, ArchiCAD 20 AUS,
Back to top
View user's profile Send private message Visit poster's website MSN Messenger   LinkedIn Profile Link (Full URL, please)
David Larrew
Veteran member
Veteran member

Joined: 28 Oct 2003
Posts: 581
Location: Austin, TX USA

PostPosted: Wed Feb 24, 2010 3:36 pm    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

Be sure to add the desired Layer to the Schedule's Criteria list (in the Scheme Settings dialog). You will need to make multiple Schedules to separate the different outputs.
_________________
David Larrew, AIA, GDLA, GSRC
Architectural Technology Specialist
a r c h i s o l u t i o n s

Dual 6-core Xeon / 24 GB / ATI HD 5870
WIN7 64 / OSX 10.6.8
AC 10-15 USA
Back to top
View user's profile Send private message Visit poster's website    LinkedIn Profile Link (Full URL, please)
Erika Epstein
Senior member
Senior member

Joined: 30 Oct 2003
Posts: 3646
Location: usa

PostPosted: Wed Feb 24, 2010 5:18 pm    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

I and others here have had trouble with overlapping zones, even when putting them on separate layers. Duane Valencia had a recent post about this problem.

I don't know what your project is but there are some workarounds.
For example with residential I have to do heat/cool area and volume. So I have my overall zones on a separate layer but move them a set distance away from the building so all the other schedules read correctly. When ther e is an update in the footprint, I update the geometry of these zones then move them back away from the main building. Tedious, but not difficult. The zone tags stay by the plan so the numbers are read as needed by the building department and others.

_________________
Erika
Architect, Consultant
MacBook Pro Retina, 15-inch Yosemite 2.8 GHz Intel Core i7 16 GB 1600 MHz DDR3
Mac OSX 10.11.1
AC5-18
Onuma System

"Implementing Successful Building Information Modeling"
Back to top
View user's profile Send private message    
ares997
Active member
Active member

Joined: 27 Jul 2007
Posts: 223
Location: Seattle, WA

PostPosted: Fri May 03, 2013 8:29 pm    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

I have been playing around with this and I think if you set the renovation status of the overall zone to the be "demolished/demolition status" and hide things to be demolished on the "planned status", then set your schedule to be on "planned status" you can isolate the information on the schedule. Still trying to figure out how to reference two zones in one schedule but as far as I have read that is not possible.
_________________
Archicad 20 (4020), Windows 10, Intel Xenon CPU E5-2643 v4 3.40GHz (64 GB RAM) & MAC OSX 10.10.3, 2.7 GHz Intel Core i7 (16 GB 1600 Mhz DDR3)
Back to top
View user's profile Send private message Visit poster's website MSN Messenger  Facebook ID (Not full URL, just ID!) LinkedIn Profile Link (Full URL, please)
NandoMogollon
Active member
Active member

Joined: 05 Dec 2006
Posts: 363
Location: Sydney NSW AU

PostPosted: Fri May 03, 2013 9:23 pm    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

Thanks for the tip, though the post is a few years old, back in 2010 we didn't have a renovation status to play with.

An alternative is to have different layer combs with zones in different layer priorities... and the schedule would work as a view, not as a viewpoint.

cheers

_________________
Nando Mogollon

www.nandomogollon.com
www.openBIMer.com
mail@nandomogollon.com
@openbimer
Now in Australia!
Revit 2017, ArchiCAD 20 AUS,
Back to top
View user's profile Send private message Visit poster's website MSN Messenger   LinkedIn Profile Link (Full URL, please)
furtonb
New member
New member

Joined: 01 Nov 2013
Posts: 7
Location: Budapest

PostPosted: Mon Jun 01, 2015 9:53 am    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

hi! I came across a similar situation: I need to schedule the equipment for each room in several variations, which I was able to do by adding the different zone numbers & renovation status as criteria (see the attached screenshot about this). my problem is: if I copy something to be in a new zone, the schedule handles the newly copied items as they were still in the zone of the original items. for some strange reason if I pick up the objects with the eyedropper, then place it, sometimes it happens, sometimes not, I wasn't able to determine what is inducing it.

workaround: I added some unique blabla to each objects' ID, which was enough to filter them, but it was so tedious. Sad

_________________
MBP| macOS 10.12.6 | AC20 INT EDU
Back to top
View user's profile Send private message    
Jussi_
New member
New member

Joined: 12 Nov 2010
Posts: 26
Location: Finland

PostPosted: Fri Nov 20, 2015 10:07 am    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

I am using multiple overlapping Zones the same way as NandoMogollon is. I am sure that majority of users end up using multiple overlapping zones, because it is logical and there is a need for various zone related data.
We have need for total zones, building face or site block zones, rental area or apartment zones etc. and finally single room/space zones. These zones (IfcSpaces) do overlap. I cannot figure out how to schedule rooms inside an apartment nor zones inside the block that is going to be build next.

Can I sort or schedule these overlapping zones some how?
Could it be possible that ArchiAD Zone does not know smaller zones that bigger one overlaps?
Back to top
View user's profile Send private message    
Alex Moruzzi
New member
New member

Joined: 05 May 2004
Posts: 28
Location: Switzerland

PostPosted: Thu Feb 11, 2016 2:37 pm    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

I must thank you all for this discussion...
I did a specific renovation status named Project and general data where I stuck the zones that are not room specific zones .
The schedules now work correctly !!!
(I also use the renovation status for specific variations)...

_________________
Archicad 19 - OSX10.10 - MBP early 2011 16G/ssd
Back to top
View user's profile Send private message AIM Address    
schagemann
Junior member
Junior member

Joined: 10 Nov 2003
Posts: 186
Location: sydney, australia

PostPosted: Mon Aug 07, 2017 4:00 am    Post subject: Re: Scheduling objects on Multiple overlapping Zones Reply with quote

Although not as automated, but more reliable (always had problems with automated zones, as there is no warning mechanism...) is the following:

1. use a custom property that is set directly on elements to be scheduled (select all objects);

2. use the hotlink master ID to associate the elements to the space in the schedule;

Until GS sorts out the zone tool this seems the best way for us.

_________________

macinteract
Design Technology Managers.
All  on macOS | since AC 6

mACT > ARCHICAD Framework
By Architects for Architects.
Back to top
View user's profile Send private message Visit poster's website    
Display posts from previous:   
View previous topic :: View next topic
Post new topic   Reply to topic   printer-friendly view       ArchiCAD-Talk Forum Index >>> Schedules >>> Scheduling objects on Multiple overlapping Zones All times are GMT + 1 Hour
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
You cannot attach files in this forum
You cannot download files in this forum


Powered by phpBB 2001, 2005 phpBB Group
Copyright 2012 - Graphisoft SE. All rights reserved worldwide. Terms of Use | Privacy Policy