I typically start the bottom of my exterior walls at the same level as the top of my foundation so that my exterior finish, such as stucco, will cover the mud sill and floor assembly. The intersection priorities of my 2x6 wall, floor assembly and 2x6 mud sill clean up accurately, except for little bit of sheet rock that misses the mud sill. See the attached picture. Can anyone suggest a way to clean this up other than masking it?