Hi,
I have a project (16 storey highrise) with interactive schedules calculating area/volumes using zones
I have placed them by hand because they are calculating different areas of the floor plan (appartments/commercial/technical etc).
I find the calculations take forever in some cases and fast for fewer zones.
BUT I don't think this should take as long as it does (in some cases up to 1,5min per sheet).
What are the criterias that slow the calculations down?
Now a publishing set of 6 different calculations can take up to 3-5 minutes to publish.
Any thought on best practices using interactive schedules?
All windows and doors using the same method also takes ages.
Thanks,
Dominicus
I have a project (16 storey highrise) with interactive schedules calculating area/volumes using zones
I have placed them by hand because they are calculating different areas of the floor plan (appartments/commercial/technical etc).
I find the calculations take forever in some cases and fast for fewer zones.
BUT I don't think this should take as long as it does (in some cases up to 1,5min per sheet).
What are the criterias that slow the calculations down?
Now a publishing set of 6 different calculations can take up to 3-5 minutes to publish.
Any thought on best practices using interactive schedules?
All windows and doors using the same method also takes ages.
Thanks,
Dominicus
*********
db-architects ltd & Arkkitehdit Korhonen & Penttinen Oy
Dominicus Björkstam
Finland
AC 22 latest build, localized FIN version
+MEP
Hardware MacbookPro 15" i9 + 32GB Ram + Windows Desktop (win10)
db-architects ltd & Arkkitehdit Korhonen & Penttinen Oy
Dominicus Björkstam
Finland
AC 22 latest build, localized FIN version
+MEP
Hardware MacbookPro 15" i9 + 32GB Ram + Windows Desktop (win10)